Bayer India, Vapi Agrochemical facility

Bayer India, Vapi Agrochemical facility
Project Information
Investment: 110 Mio.
- 16 Pilot and production scale Multi purpose units (MPU)
- Flexible Train concept
- 16 Reaction / Crystallization Trains
- 5 Distillation Trains
- 5 Drying Trains
Rector Size 0,25 up to 12 m³
Intermediates / Feed supply from Containers or Tank Farm
Filling / packing for Liquids (Drums, Container) and solids
(Sacks, Drums, Big Bags)
Central transfer stations (piped connections)
Utilities:
Heating cooling System (-20°C / +180°C)
- Steam
- Demineralised water
- Cooling water
- Nitrogen
- Instrument Air
- Ammonia
Responsibilities
- Basic Engineering Review
- Detailed Engineering
- Procurement Assistance
- Execution Support